ContID 253062 EST NO 0001 |
Date:08/28/2025 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 253062 | Estimate Number | 0001 | Estimate Type | DRAFT_PROGRESS | ||
District Office | SOMERSET (08340) Phelps, Lindsey B. | ||||||
Contractor | GADDIE-SHAMROCK LLC | MARS ADDR SN 0 | |||||
PO BOX 280 | |||||||
COLUMBIA , KY , 42728 | |||||||
Pay Period | 07/14/2025 TO 08/22/2025 | ||||||
Date Approved | 08/26/2025 | ||||||
Primary Proj Number | 0800105332501 | ||||||
Project No. | CB06 001 0533 000-001, CB06 001 0533 001-004, CB06 001 0768 029-031, CB06 001 2973 000-002 | ||||||
Primary County | ADAIR | ||||||
Name of Road | VARIOUS ROADS IN ADAIR CO | ||||||
Description | FROM METCALFE / ADAIR CO LINE, EXTENDING EASTERLY TOWARDS FR ED FUDGE RD (CR 1907). | ||||||
Date Let | 06/26/2025 | Formal Acceptance | |||||
Date Awarded | 07/09/2025 | Date Work Began | |||||
Date Contract Executed | 07/14/2025 | Open To Traffic | |||||
Date NTP Issued | 07/14/2025 | Actual Completion Date | |||||
Current Contract Amount | $526,600.03 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $526,600.03 |
Total Earnings | $137,232.29 |
$0.00 |
$137,232.29 |
|
Percent Complete | 26.06 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $389,367.74 |
Gross Earnings | $137,232.29 |
$0.00 |
$0.00 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $137,232.29 |
$0.00 |
137,232.29 |
|||
Contract Id | 253062 | Change Order Summary |
County | ADAIR | ||||||
Estimate Nbr | 0001 | Project Number | CB06 001 0533 000-001, CB06 001 0533 001-004, CB06 001 0768 029-031, CB06 001 2973 000-002 | |||||||
Contractor | GADDIE-SHAMROCK LLC | Period | 07/14/2025 TO 08/22/2025 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 253062 | COMMONWEALTH OF KENTUCKY |
County | ADAIR | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 0800105332501 | ||||||
Estimate Nbr | 0001 | Period | 07/14/2025 TO 08/22/2025 | |||||||
Contractor | GADDIE-SHAMROCK LLC | |||||||||
Project | 0800105332501 | Fed/State Project Number | CB06 001 0533 000-001 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0005 | LEVELING & WEDGING PG64-22 | 00190 | TON | 144.00 | 144.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0010 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 660.00 | 660.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0015 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 6.00 | 6.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0025 | EDGE KEY | 02585 | LF | 42.00 | 42.000 | 0.000 | 0.000 | 50.00 | 0.00 | |||
0030 | MAINTAIN & CONTROL TRAFFIC (KY 533) | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,500.00 | 0.00 | |||
0035 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 2,500.00 | 2,500.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0040 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 9,750.00 | 9,750.000 | 0.000 | 0.000 | 0.32 | 0.00 | |||
0045 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,251.00 | 1,251.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0050 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 3,143.00 | 3,143.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0800105332501 | Fed/State Project Number | CB06 001 0533 000-001 | Category | 0002 DEMOBILIZATION | |||||||
0055 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,981.25 | 0.00 | |||
SUBTOT | $0.00 |
$0.000 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |
Project | 0800105332502 | Fed/State Project Number | CB06 001 0533 001-004 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0060 | LEVELING & WEDGING PG64-22 | 00190 | TON | 184.00 | 184.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0065 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,005.00 | 1,005.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0070 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 9.00 | 9.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0075 | TEMPORARY SIGNS | 02562 | SQFT | 330.00 | 330.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0080 | MAINTAIN & CONTROL TRAFFIC (KY 533) | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,500.00 | 0.00 | |||
0085 | MOBILIZATION FOR MILL & TEXT (KY 533) | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 12,050.00 | 0.00 | |||
0090 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 40.00 | 40.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0095 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 3,500.00 | 3,500.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0100 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 14,500.00 | 14,500.000 | 0.000 | 0.000 | 0.32 | 0.00 | |||
0105 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 46.00 | 46.000 | 0.000 | 0.000 | 14.00 | 0.00 | |||
0110 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,851.00 | 1,851.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0115 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 4,649.00 | 4,649.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0800105332502 | Fed/State Project Number | CB06 001 0533 001-004 | Category | 0002 DEMOBILIZATION | |||||||
0120 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,981.25 | 0.00 | |||
SUBTOT | $0.00 |
$0.000 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |
Project | 0800107682501 | Fed/State Project Number | CB06 001 0768 029-031 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0125 | LEVELING & WEDGING PG64-22 | 00190 | TON | 181.00 | 181.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0130 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 830.00 | 830.000 | 0.000 | 0.000 | 104.50 | 0.00 | |||
0135 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 8.00 | 8.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0140 | TEMPORARY SIGNS | 02562 | SQFT | 190.00 | 190.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0145 | MAINTAIN & CONTROL TRAFFIC (KY 768) | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,500.00 | 0.00 | |||
0150 | MOBILIZATION FOR MILL & TEXT (KY 768) | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 12,050.00 | 0.00 | |||
0155 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 30.00 | 30.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0160 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 2,000.00 | 2,000.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0165 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 8,000.00 | 8,000.000 | 0.000 | 0.000 | 0.32 | 0.00 | |||
0170 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 24.00 | 24.000 | 0.000 | 0.000 | 14.00 | 0.00 | |||
0175 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,574.00 | 1,574.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0180 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 3,953.00 | 3,953.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0800107682501 | Fed/State Project Number | CB06 001 0768 029-031 | Category | 0002 DEMOBILIZATION | |||||||
0185 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,981.25 | 0.00 | |||
SUBTOT | $0.00 |
$0.000 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |
Project | 0800129732501 | Fed/State Project Number | CB06 001 2973 000-002 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0190 | LEVELING & WEDGING PG64-22 | 00190 | TON | 224.00 | 224.000 | 221.930 | 0.000 | 221.930 | 104.50 | 23,191.68 | 23,191.68 | |
0195 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,025.00 | 1,025.000 | 1,022.960 | 0.000 | 1,022.960 | 104.50 | 106,899.32 | 106,899.32 | |
0200 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 10.00 | 10.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0205 | TEMPORARY SIGNS | 02562 | SQFT | 250.00 | 250.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0210 | MAINTAIN & CONTROL TRAFFIC (KY 2973) | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,500.00 | 2,500.00 | 2,500.00 | |
0215 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 3,750.00 | 3,750.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0220 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 15,000.00 | 15,000.000 | 14,504.000 | 0.000 | 14,504.000 | 0.32 | 4,641.28 | 4,641.28 | |
0225 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 40.00 | 40.000 | 0.000 | 0.000 | 14.00 | 0.00 | |||
0230 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,944.00 | 1,944.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0235 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 4,883.00 | 4,883.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0800129732501 | Fed/State Project Number | CB06 001 2973 000-002 | Category | 0002 DEMOBILIZATION | |||||||
0240 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,981.25 | 0.00 | |||
SUBTOT | $137,232.28 |
$137,232.285 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |